New Hampshire and Greater Boston Solution Project, US
The project was proposed by Eversource and National Grid to meet the rising power demand in Greater Boston and southern New Hampshire.
Read MoreMarch 29, 2018
The project was proposed by Eversource and National Grid to meet the rising power demand in Greater Boston and southern New Hampshire.
Read MoreDecember 6, 2017
Eversource Energy and National Grid have completed the construction works of the Merrimack Valley Reliability Project (MVRP) on schedule.
Read MoreOctober 26, 2016
A number of New Hampshire-based companies have been selected by Eversource to begin the first phase of constructing the Merrimack Valley Reliability Project transmission line. Eversource and National Grid are jointly developing the project.
Read MoreJuly 15, 2016
The New Hampshire Site Evaluation Committee has voted to approve construction of the Merrimack Valley Reliability Project (MVRP) proposed by Eversource Energy and National Grid.
Read MoreMarch 10, 2016
The Merrimack Valley Reliability Project is a 345 kV project involving the construction of a 24-mile (38.64-km) line from the Scobie Pond substation in Londonderry, New Hampshire, to Tewksbury, Massachusetts.
Read MoreFebruary 18, 2015
The Independent System Operator (ISO) New England (ISO-NE) has chosen the alternating current (AC) transmission proposal of Eversource (formerly Northeast Utilities) and National Grid as the preferred solution to bolster the region’s power grid in the Greater Boston area to ensure continued reliability into the future.
Read MoreJanuary 27, 2015
The ISO New England (ISO NE) is likely to announce its decision on the two transmission projects proposed by NextEra, National Grid, and Northeast Utilities on February 18, 2015.
Read MoreDecember 1, 2014
Massachusetts regulators are seeking public comments on two transmission projects proposed by NextEra, National Grid, and Northeast Utilities.
Read More