Nigeria’s federal government has restored the 330 kV Benin–Egbin transmission line, increasing electricity supply to the Lagos power complex to more than 1,000 MW, although outages continue in parts of Lagos and other areas. The line’s return to service on November 9, 2026, followed repairs that had been completed after its unavailability reduced transmission capacity […]